We are all painfully aware of the $19 million overrun on the Bay Street / Mill Street / Craigleith water systems project. Analysis of root causes and remedies is in process. Among other concerns and considerations, we believe two particular issues must be investigated.
1) Is our Asset Management Plan (AMP), conducted a few years ago and intended to give us a clear picture on the status of our current infrastructure viable?
Not having a handle on the condition of some of our water infrastructure was a big contributor to the scale of the budget overage, and it being such a surprise. The AMP must be reviewed and updated. That process can't be carried out in a few months, but the need for the review can be established and the review exercise scoped.
2) The concept of public Municipal Service Corporations has recently been getting much more attention.
Those who attended the recent BMRA Annual General Meeting would have been introduced to the idea of an MSC.
In simple terms, it allows for a regional approach to be taken to planning, constructing and running municipal infrastructure, such as water and wastewater. It is run by a third party organization, but is not a private entity. An MSC can follow natural systems, like water sources and actual settlement patterns, instead of municipal boundries.
It allows for economies of scale, longer financing terms and non-political infrastructure planning decisions. The appropriateness of an MSC for our town would have to be determined, but the Province is currently evaluating the introduction of one for Simcoe County, including Collingwood. Our Council should state its interest in being included in the analysis of the Simcoe MSC, so that the Town would be in a position to determine its potential role in the future of TBM infrastructure.